How to Create a Gantt Chart in Microsoft Project

Laptop showing linked task bars and a milestone, illustrating a Gantt chart in Microsoft Project

Creating a Gantt chart in Microsoft Project is largely automatic. Start a blank project, set the start date, enter your tasks and durations in the Gantt Chart view, link them with dependencies, and Project draws the bars, arrows and milestones on the timeline. The skill is in structuring tasks so the chart stays accurate when plans change.

Key takeaways

  • The Gantt Chart view is Project’s default; every task you type becomes a bar.
  • Switch tasks to Auto Scheduled so dates move when durations or links change.
  • Link tasks with Task > Link Tasks (finish-to-start by default) to create dependencies.
  • A task with 0 duration becomes a milestone diamond.
  • Tick Critical Tasks on the Gantt Chart Format tab to show the critical path in red, and set a baseline before work starts.

What is a Gantt chart in Microsoft Project?

A Gantt chart in Microsoft Project is a two-part view: a task table on the left listing names, durations, dates and predecessors, and a bar chart on the right plotting each task against a calendar. Arrows show dependencies, diamonds mark milestones, and summary bars group phases. It is the view Project opens by default.

Unlike a Gantt chart drawn in Excel, Project’s chart is driven by a scheduling engine. Change one task’s duration and every linked task after it moves automatically, which is the main reason to use Project rather than a spreadsheet.

Gantt element What it shows How you create it
Task bar Start, finish and duration of a task Type a task name and duration
Summary task A phase that rolls up its subtasks Indent tasks under it (Alt + Shift + Right arrow)
Link arrow Dependency between two tasks Task > Link Tasks
Milestone diamond A key date or deliverable Set duration to 0
Red bar Task on the critical path Gantt Chart Format > Critical Tasks
Grey baseline bar Original plan for comparison Project > Set Baseline (Tracking Gantt view)

How to set up a new project before adding tasks

Before typing tasks, create a blank project, set the project start date, check the working calendar and switch new tasks to automatic scheduling. These settings decide where every bar lands, so getting them right first saves you rescheduling the whole chart later.

  1. Open Project and select Blank Project, or pick a template if one matches your work.
  2. Go to Project > Project Information and enter the Start date.
  3. Under Project > Change Working Time, check working days, hours and add bank holidays.
  4. At the bottom-left status bar, click New Tasks and choose Auto Scheduled.
  5. Save the file (.mpp) with a clear name.

New projects default to Manually Scheduled tasks, where Project doesn’t move dates for you. That suits rough planning, but most people expect the chart to update automatically, which only happens with Auto Scheduled tasks.

If you have not installed Project yet, our Project 2024 Professional install and activation guide walks through it.

Project manager setting a start date and working calendar before building a Gantt chart in Microsoft Project

How to create a Gantt chart in Microsoft Project

To create a Gantt chart in Microsoft Project, open the Gantt Chart view, type each task in the Task Name column with its duration, indent subtasks under phase names to create summary tasks, then link the tasks in order. Project plots the bars on the timeline as you type.

  1. Select View > Gantt Chart (it is usually already open).
  2. In the first empty row of Task Name, type a phase, for example “Design”.
  3. Type the tasks in that phase on the rows below, such as “Gather requirements” and “Draft wireframes”.
  4. Select those tasks and press Alt + Shift + Right arrow, or choose Task > Indent Task. “Design” becomes a summary task.
  5. Enter a Duration for each subtask, for example 3d for three days or 2w for two weeks. Leave summary durations alone; Project calculates them.
  6. Repeat for each phase, then link the tasks (next section).
  7. Right-click the chart’s timescale and choose Timescale, or use the zoom slider, to fit the bars on screen.

Tips for a cleaner task list

  • Use verb-noun names (“Approve design”) so each bar describes an action.
  • Keep most tasks between one day and two weeks; very long tasks hide problems.
  • Avoid typing start and finish dates on Auto Scheduled tasks. That creates constraints that stop Project rescheduling them.

Select two or more tasks in the Task Name column, holding Ctrl for non-adjacent ones, and choose Task > Link Tasks. Project creates a finish-to-start link by default, so the second task can’t begin until the first ends. You can also type predecessor IDs straight into the Predecessors column.

Microsoft’s guide to linking tasks in a project covers every method. To change a link type, double-click the arrow on the chart and choose from the Type list.

Link type Code Meaning Example
Finish-to-start FS B starts when A finishes Pour foundations, then build walls
Start-to-start SS B starts when A starts Start testing once coding begins
Finish-to-finish FF B finishes when A finishes Documentation ends with development
Start-to-finish SF B finishes when A starts Old system runs until new one starts

Lag and lead time

Add a delay or overlap by typing it after the predecessor. 3FS+2d means “start two days after task 3 finishes”, for example waiting for paint to dry. 3FS-1d overlaps by a day. Use lag instead of fixed dates so the plan still moves when task 3 slips.

A common mistake is linking summary tasks to each other and to their subtasks at the same time. Link the detailed tasks instead; it keeps the logic clear and avoids confusing circular links.

Milestones, the critical path and baselines

Milestones mark key dates, the critical path shows which tasks control the finish date, and a baseline saves a snapshot of the plan to compare against. Add milestones by setting a task’s duration to 0, show the critical path from the Gantt Chart Format tab, and set a baseline from the Project tab before work starts.

Add a milestone

Type the milestone name, such as “Design signed off”, enter 0 in Duration and press Enter. A diamond appears on the chart. Microsoft’s add a milestone guide also explains marking a longer task as a milestone.

Show the critical path

Choose View > Gantt Chart, open the Gantt Chart Format tab and tick Critical Tasks. Critical tasks turn red. Any delay to a red task pushes back the whole project, so that is where to focus your attention and resources.

Set a baseline

Once the plan is agreed, choose Project > Set Baseline > Set Baseline, select Entire Project and click OK. Project can store up to 11 baselines. Switch to View > Tracking Gantt to see the original plan as grey bars beneath current progress.

Planning bigger projects with shared resources?

Project Standard handles Gantt charts, links and baselines for one planner. Project 2024 Professional adds tools such as Team Planner and resource conflict handling; our Project Standard vs Professional comparison explains when the extra features pay off.

How to format, print and share the Gantt chart

Use the Gantt Chart Format tab to change bar styles, colours and labels, add the Timeline view for a simple summary, and export to PDF for people who don’t have Project. Printing works best with File > Print and the page setup adjusted to fit the date range on landscape pages.

  • Bar styles: Gantt Chart Format > Format > Bar Styles changes colours for tasks, summaries and milestones.
  • Labels: show resource names or dates beside bars from the same dialog’s Text tab.
  • Timeline: tick Timeline on the View tab, then add key tasks to it for a one-line summary you can copy into PowerPoint or email.
  • PDF export: File > Export > Create PDF/XPS Document gives stakeholders a read-only copy.
  • Reports: Report > Dashboards > Project Overview gives a quick status page.

For process maps that sit alongside the schedule, many teams pair Project with Visio. Our guide on making a flowchart in Visio shows how. If you need a lighter alternative for small task lists, Excel formulas and conditional formatting can produce a basic chart, though without automatic rescheduling.

Frequently asked questions

Does Microsoft Project create a Gantt chart automatically?

Yes. The Gantt Chart view is the default view in Project desktop, and every task you enter with a duration appears as a bar on the timeline straight away. Linking tasks adds dependency arrows, and summary tasks appear when you indent subtasks. You do not need to draw anything by hand.

Why don’t my Gantt bars move when I change a task?

The tasks are probably set to Manually Scheduled, which is the default for new projects. Select the tasks and choose Task > Auto Schedule, and set New Tasks to Auto Scheduled on the status bar. Also check for typed start dates, which add constraints that stop Project moving the task.

What is the difference between Gantt Chart and Tracking Gantt?

The Gantt Chart view shows the current schedule. Tracking Gantt shows the current schedule with the saved baseline underneath as grey bars, plus progress shading, so you can see which tasks have slipped. Set a baseline first, or Tracking Gantt has nothing to compare against.

Can I make a Gantt chart in Project Standard?

Yes. Project Standard 2024 includes the Gantt Chart view, task linking, milestones, critical path and baselines. Project Professional adds features such as Team Planner and connection to Project Online, which matter more for teams sharing resources across projects than for building the chart itself.

How do I show the critical path in Microsoft Project?

Go to View > Gantt Chart, open the Gantt Chart Format tab and tick Critical Tasks. Tasks on the critical path turn red. In other views, use View > Highlight > Critical or filter by Critical. Any delay to these tasks moves the project finish date unless you add resources or change links.

How many baselines can I save in Project?

Project lets you save up to 11 baselines in a single file: Baseline plus Baseline 1 to 10. Set the first when the plan is approved, then save extra baselines at key points such as phase reviews. Comparing them shows how the plan has changed over time.

The bottom line

A Gantt chart in Microsoft Project is mostly about good inputs: auto-scheduled tasks, sensible durations, proper links, a few milestones and a baseline. Get those right and Project keeps the chart accurate for you; see our Project Standard vs Professional guide if you are choosing a version.

Resource Why it helps
Project 2024 Professional install guide Install and activate Project first
Project Standard vs Professional Choose the right edition
Make a flowchart in Visio Map processes alongside your schedule
Excel formulas for beginners Lighter option for simple task lists
Project 2024 Professional Licence for Project desktop
Link tasks in a project (Microsoft) All ways to create dependencies
Add a milestone (Microsoft) Zero-duration and longer milestones
Show the critical path (Microsoft) Highlight tasks that drive the finish date